I know this thread is a couple months old, but wanted to chime in.
We are been in the implementation phase for the last 9 months. We started mid-August 2021. Unfortunately, Vena implementation has not gone as we had hoped. We have a phenomenal Vena consultant and project manager, but the process is what has been lacking.
The 4 days of online training before we started with our lead consultant left more questions than answers. The training started us in the middle of a process and how that process worked. But we were still not clear on how we got to that process, thus we couldn't build upon what we learned. Instead we pieced together what we learned to figure it out. It would have been helpful for us to start at the beginning and work our way through the entire process. During Paul Barnhurst's Excelerate 2022 session, his discussion of the Design & Build Process immediately made me think of how this training/implementation has gone. I feel like we discussed step 1 (1. Plan model (question being answered), but then jumped into step 7 of model building (7. Complete cover sheet, exec summary). What I mean by this is that the Vena team asked us questions, then built the reports/templates for us (including all the behind the scenes stuff) and then we verified that all the numbers tied out. We very much wanted to be able to understand ALL the behind the scenes stuff, how the reports/templates were built and how they function, then verify all the numbers. We asked for time to watch how all the behind the scenes stuff was made and reports/templates were built/function, but that didn't happen. It wasn't in scope. We felt confident during demo's that from what we learned we would be able to be self-sufficient and know how to do everything ourselves.
After 9 months, we are now able to do a lot of the basic mappings and functionality. But that didn't come to fruition until month 5-6, during a coaching session. During that session we were taught the extreme basics of how to map a template. And since that point we HAVE been able to build our own templates, but it wasn't until then did I understand how it all worked together. We are a relatively savvy excel team. We wouldn't have taken on the project if we didn't think we could have been self-sufficient, but it just took a long time. I really thought we would have completed implementation in 8 weeks like we had originally planned. The timeline of implementation is not entirely a reflection of the Vena process. We had to include time to still complete all our normal job duties, including month end close each month. We are lean, but we are all about process improvement.
One of the other expectations of Vena was the drill down process (there are a couple different ways to do this, I'm referencing the Zoom In/Out). It does drill down/zoom in/out, but it is extremely slow. We are not a large company, so we can't figure out why it is so slow for us. Not sure if our hierarchy is too big or if there are too many mappings? We know there are very large Vena customers and we are tiny compared to them. We have asked. And it all depends. If anyone is able to use the Zoom In/Out function in a very quick manner please let me know how you do it. I cannot show my VP of Finance this functionality without embarrassment, so I definitely can't show this functionality to any other executive level or board member.
I am still PRO Vena even though our implementation has been off to a slow/rocky start. I wanted to mostly share so that new customers know that if they are expecting a start at the beginning and work your way through the entire process along side your consultant that will NOT be happening. This is not my first implementation, so I have had the opportunity to start from beginning to end. There is a difference. But if you are wanting for someone else to build the process, templates, reports, integrations, calculations, etc for you then this is what you can expect.
Again, this is not a reflection of the Vena people, they are amazing and have followed the scope. I'm glad it sounds like we are an exception. I suppose there has to be one.
Thanks,
Carrie
------------------------------
Carrie Billings
Assistant Controller
Indiana Institute of Technology
------------------------------
Original Message:
Sent: 03-29-2022 17:11
From: Brendan Eger
Subject: Implementing Vena
I recently watched the demo portion of The Not For Profit Pros Meetup and Demo, which I wasn't able to catch earlier (even though I was on the panel...) and found that the templates used in the demo were really interesting and approach things very differently than how we do. Like @Josh Weinberg and I mentioned earlier in this thread, Vena's flexibility to build nearly exactly what we had previously was a huge benefit for us, I'm finding more and more that many of us are working in a vacuum and could really benefit from developing/sharing some best practices. As much as we might think that our challenges are unique, we're actually not alone and we can help each other think through better approaches to template/report/data model design choices that allow us to collect and visualize the most important information, but do so in more efficient ways.
------------------------------
Brendan Eger
Original Message:
Sent: 03-10-2022 11:44
From: David Cornfield
Subject: Implementing Vena
I would like to hear from people their experience in implementing Vena. I think that would help new Vena implementers.
Of course, the first hurdle is the training for setting up templates and reports. It is necessary to have the full 4 days of training. Key is getting the people with the skills and aptitude necessary to set up the Vena spreadsheets. It takes time to set up but with the training it will move along very well.
The modeling was fairly easy. We had already thought about what we needed and wanted. It is fairly easy to do in Vena.
For us (WWF-Canada), I think one pain point was the automated uploading of data from our accounting system (MS Dynamics GP - 2018) into Vena. We had hired one person who did the coding which worked for a couple of months and then stopped working after our fiscal year end. We had to go to another consulting vendor to do the coding correctly. Live and learn I guess. Anyway, it took time to get that done correctly, but once it started working properly we don't have to even think about it. It automatically loads up the data 4am even day - no issues.
So, how was your experience implementing Vena?
------------------------------
David Cornfield
------------------------------